Agricultural structure application or full building permit: which fits a new outbuilding near St. Anthony?
Published: 2026-11-06 · Updated: 2026-11-06 By Kjel Jones — independent custom-home researcher for St. Anthony and the Fremont County valley floor. Not a builder and not a general contractor. Licensed Idaho real estate agent, LPT Realty.
Fremont County gives a new outbuilding on county ground two doors: the Agricultural Structure Application (2026 revision, retrieved 19 August 2026) and the full building permit run against the county's Pre-Construction Check List for Building Permits, rev. 17 April 2026 (retrieved 14 August 2026). Our agricultural building exemption guide explains the exemption on its own; this page sets the two paths side by side so you can see which one your building actually fits.
The two paths side by side
| Dimension | Agricultural structure application | Full building permit |
|---|---|---|
| Up-front fee | A fee of $100, printed on the form itself | Permit fee based on square footage and construction type, plus a $50.00 site plan review fee |
| Review time | A stated review period of 7 to 10 working days | Four to six weeks |
| What it asks for | Property details including section, township, range and parcel number, plus the size of the parcel and the size of the building | A complete application with the parcel, section, township and range, a deposit on submittal, the $50 site plan review fee, two sets of plans with engineering calculations and truss designs |
| Plans standard | Not stated in the banked material — a named gap below | "ALL FREE-STANDING POST & BEAM STRUCTURES REQUIRE ENGINEERED STAMPED PLANS." |
| Allowed use | A structure for storing or maintaining equipment and machinery used exclusively in agricultural operations | Any use, built to code |
| How long it lasts | Not banked | Two years, stated plainly |
| Where filed | Planning & Building Department at 125 N. Bridge St. Suite 1, St. Anthony | The county building permit desk — see two clocks on your permit |
Sources: Fremont County Agricultural Structure Application, 2026 revision (retrieved 19 August 2026) and Fremont County Pre-Construction Check List for Building Permits, rev. 17 April 2026 (retrieved 14 August 2026), as banked on agricultural-building-exemption, zoning-permit-comes-first, barndominium-st-anthony and two-clocks-on-your-permit.
Choose the agricultural application when
- The building will hold "equipment and machinery used exclusively in agricultural operations" — the form's own test.
- The public will never use it. Use by people who are not the owners or employees of the farm disqualifies the exemption.
- No one will live, sleep or cook in it — the form defines a place of human habitation as a space for living, sleeping or cooking, and that use is out.
- You can honestly sign the certification that the use will stay true to that description, because the form makes you sign exactly that.
Choose the full building permit when
- Any part of the building's future is non-agricultural: a place of employment where agricultural products are processed, treated or packaged; use by the public; or habitation.
- You are building free-standing post and beam — engineered stamped plans are required on the permit path, and that requirement is real whichever door you walk through.
- You want the stated two-year permit life rather than an approval whose duration no banked document states.
- Retrofitting compliance later would cost more than the code build does now — the deciding question on our exemption page.
The fee is the small difference
The ag application is a flat $100. The permit path carries the checklist's own words: "A $50.00 fee will be charged for the site plan review. If you bring your plans back for a change after approval, you will be charged an additional site plan review." — with the permit fee itself based on square footage and construction type. These are fixed public fees set by the county's documents, not quotes; the permit fee's dollar amount is not printed in the banked material, so get the number from the desk before pricing either path. Our custom home cost page carries the fee rows behind this table.
Where the two paths meet
Near Stanford Field, the overlay erases the distinction. Asked whether exempt ag buildings still need permits inside it, that page answers: "If they exceed 30 feet, yes." The code expands permit requirements inside the overlay to include construction of any building or structure more than 30 feet in height that is otherwise exempt from a permit, and states in parentheses that this includes agricultural outbuildings and similar accessory structures. Tall and near the runway, there is one path.
One boundary to name plainly: no banked page says whether the City of St. Anthony offers any agricultural exemption inside the city limits — this comparison covers county ground only.
What you sign on the ag side
The application's Section 3 Acknowledgement (2026 revision, retrieved 19 August 2026) puts the stakes in one sentence: "I hereby certify that the building's use will stay true to the description above; and that if the use of this building is found to be in violation of the above description, this permit may be revoked." And the penalty text is specific: "A wilful violation is a misdemeanour, punishable by a fine of not more than three hundred dollars, or imprisonment for not more than ninety days, or both." Worse, "Each day the violation continues constitutes a separate offense." The saving is $100 and some weeks; the exposure is not.
Named gaps — not banked, so not claimed
- Whether the agricultural application asks for any drawings or engineering: the banked pages list only property details and building size.
- How long an agricultural structure approval stays valid: not banked.
- The county building permit fee amount: printed only as based on square footage and construction type.
- Any agricultural exemption inside the St. Anthony city limits: not banked.
Frequently asked questions
How much cheaper is the agricultural application up front?
A fee of $100, printed on the form itself, versus the $50.00 site plan review fee plus a permit fee based on square footage and construction type. The permit fee's dollar amount is not banked.
How long does each path take?
The agricultural application carries a stated review period of 7 to 10 working days; the county building permit states four to six weeks.
What uses break the exemption?
Three declared uses: a place of employment where agricultural products are processed, treated or packaged; use by the public, meaning people who are not the owners or employees of the farm; and a place of human habitation, which the form defines as a space for living, sleeping or cooking.
What happens if an exempt building is used the wrong way?
The permit may be revoked, and a wilful violation is a misdemeanour, punishable by a fine of not more than three hundred dollars, or imprisonment for not more than ninety days, or both; each day the violation continues constitutes a separate offense.
Does the airport overlay change the choice?
Inside the Stanford Field overlay, any building or structure more than 30 feet in height that is otherwise exempt from a permit requires one — including agricultural outbuildings and similar accessory structures.
Which should I pick if the building might gain a shop or apartment later?
On the banked pages' own logic, if the building has any non-agricultural future, build to the code from the outset — retrofitting compliance later is substantially more expensive than building to the code from the outset.
Before you draw anything
Confirm the use question at the Planning & Building Department at 125 N. Bridge St. Suite 1, St. Anthony, and settle the future-use question before anyone is paid to draw — the exemption page carries the full test. If you are weighing a build on either path around St. Anthony, call (208) 656-1745 and we will talk through the ground.