Published
What a city utility hookup costs in St. Anthony: the rate sheet, the deposit, and the $4,493 line
One heading, one table, every number
The City of St. Anthony publishes its utility rates on a single page of its website, under a heading that carries the date that matters:
“Utility Rates Effective October 1st, 2025”
— City of St. Anthony, Utilities page. Retrieved 17 October 2026
That heading is doing real work. Rates change, and a builder who budgets from a two-year-old screenshot budgets wrong. The full monthly bill a St. Anthony household or job site can expect, exactly as the city’s table prints it:
| Service | Residential | Commercial |
|---|---|---|
| Water | $34.32 base + $0.68 per 1000 gallons | $39.39 base + $0.68 per 1000 gallons |
| Sewer | $38.48 base + $1.70 per 1000 gallons of average winter water usage | $38.48 per EDU + $1.70 per 1000 gallons of average winter usage |
| Sanitation cart (95 gallon) | $21.39 per month; additional cart $11.76 | $25.65 per month; additional cart $15.55 |
| Commercial sanitation | — | $10.08 per yard + $4.65 account administration fee |
| Late charge | $9.21 per month | $9.21 per month |
Two footnotes the table carries:
- Carts are picked up every Friday except holidays.
- Commercial yard service runs Tuesdays and Fridays when a second pickup is required.
On the sewer line, the city prices commercial accounts by EDU, and says so in one sentence:
“The number of EDUs are based on type/use of the facility.”
— City of St. Anthony, Utilities page. Retrieved 17 October 2026
An EDU is an Equivalent Dwelling Unit — the city converts what a building is used for into household-equivalents and bills that count. A shop with a break room is not priced like a restaurant.
The charges that only hit a new hookup
Monthly rates are the recurring bill. A new connection triggers a different set of lines — System Development Charges, which the city lists separately, for new hookups only:
| System Development Charge | Amount as published |
|---|---|
| Water | $4,493 — $1,870 plus materials; a 1-inch meter costs $2,623 |
| Sewer | $1,700 — $1,600 plus materials; currently costs $100 |
| Commercial | Call for estimate — additional charges may apply depending on size of lines installed |
The sewer line, in the city’s own words:
“Sewer: $1,700 ($1,600 plus materials - currently costs $100).”
— City of St. Anthony, Utilities page. Retrieved 17 October 2026
Read the parentheticals carefully — they are not decoration:
- The water charge is $1,870 plus materials, and the city names the meter as the cost driver at $2,623; together that is the $4,493 figure.
- The sewer charge works the same way, with materials currently at $100.
And for anything beyond a standard service, the city does not publish a number at all:
“Commercial System Development Charges: Call for estimate - additional charges may apply depending on size of lines installed.”
— City of St. Anthony, Utilities page. Retrieved 17 October 2026
“Depending on size of lines installed” is the phrase to take to the city before you close on a commercial parcel — a long service extension can move that number more than the building does.
The deposit: priced by your history
Activation of the account requires a deposit, and the city prices it from the property’s record:
“Deposit is required upon activation of account. Rate will be determined by the previous year’s usage for each property.”
— City of St. Anthony, Utilities page. Retrieved 17 October 2026
Which raises the obvious question for anyone building new — a just-created account has no last year. The city answers it directly:
“If there is no usage history for the property the deposit will be $160.00.”
— City of St. Anthony, Utilities page. Retrieved 17 October 2026
For a spec builder or an investor holding a house as a rental, the page also carries the paperwork that matters:
- an Application and Contract for Utility Service;
- a Privacy Act information notice;
- and a Landlord/Tenant Guarantee Agreement — the document that puts a tenant’s utility debt behind a property owner’s guarantee.
All three sit on the city’s utilities page.
Outside the city limits: the one-and-a-half rule
The city will serve addresses beyond its boundary — at a premium it states as a multiplier:
“Residents and Businesses outside the City limits will be billed at 1½ times the regular base rates listed above. No additional charges apply on the usage rates.”
— City of St. Anthony, Utilities page. Retrieved 17 October 2026
The split is precise and worth quoting twice:
- the base rates carry the 1½ multiplier;
- the usage rates do not.
A heavy water user just outside the line pays one-and-a-half on the $34.32 and $38.48 bases — not on every gallon. Whether a parcel is inside or outside is not always obvious from the ground:
- the desk that answers it is covered in our page on which government issues your permit;
- the belt of county-governed ground around town is mapped in the Area of City Impact guide;
- if city service is the reason a parcel would ever come inside the line, the mechanics are in how annexation into St. Anthony works — including the consent a utility connection itself can imply.
What the hookup bill has to do with your permit
Inside the city, utilities and permits are not separate conversations:
- Fees before the permit. As our water-and-sewer page puts it, the city wants its hookup fees paid before it will approve the building permit — so the SDC lines above land in the same week as the permit, not after framing.
- The capacity behind the policy. The city’s water and sewer capacity picture behind that policy — the wells, the plant headroom, the 300-foot connection rule — is walked in the connection guide.
- Zoning first. The sequence starts earlier than either bill: zoning approval comes first, every time.
None of this is a fringe cost. In the city’s own 2023 community survey, residents ranked roads first and water, sewer, and trash second among spending priorities — the people already paying these bills put them near the top. The full survey is counted out on the survey page. For budgeting a build against them, the fixed public costs on both sides of the city line are assembled in the custom-home cost page.
Reading the bill before you commit
- Ask for the SDC number in writing. Residential water and sewer publish flat; commercial is “call for estimate,” and the estimate is where line length lives.
- Check the effective date on any rate sheet you are handed. The current sheet is dated October 1st, 2025; anything older is a different bill.
- Price the deposit into closing. A new account with no history budgets $160.00 — small, but it is due at activation.
- Know which side of the line you are on before you model the monthly bill. The 1½ multiplier changes the math on every base rate. We build these comparisons into every estimate — (208) 656-1745.
Common questions
How much does it cost to connect to city water in St. Anthony?
For a new hookup, the city's published System Development Charge for water is $4,493 - $1,870 plus materials, with a 1-inch meter costing $2,623. After connection, the residential base rate is $34.32 per month plus $0.68 per 1000 gallons.
How much is the sewer connection charge in St. Anthony?
The published sewer System Development Charge is $1,700 - $1,600 plus materials, which the city currently prices at $100. Monthly, residential sewer is a $38.48 base rate plus $1.70 per 1000 gallons of average winter water usage.
What is the utility security deposit in St. Anthony?
A deposit is required when the account is activated. The rate is determined by the property's previous year of usage; if the property has no usage history - the normal case for new construction - the deposit is $160.00.
What do St. Anthony utilities cost per month?
Per the rate sheet effective October 1st, 2025: water base $34.32 (plus $0.68 per 1000 gallons), sewer base $38.48 (plus $1.70 per 1000 gallons), and a 95-gallon sanitation cart at $21.39. Commercial accounts have their own base rates and are billed sewer by EDU.
Do utilities cost more outside the St. Anthony city limits?
Yes on the base rates, no on usage. The city bills residents and businesses outside the city limits at 1.5 times the regular base rates, with no additional charges on the usage rates.
What is an EDU on a St. Anthony utility bill?
EDU stands for Equivalent Dwelling Unit. Commercial sewer is billed $38.48 per EDU plus the usage rate, and the city states that the number of EDUs is based on the type and use of the facility.
When did the current St. Anthony utility rates take effect?
The city's rates page is headed 'Utility Rates Effective October 1st, 2025.' Any figure older than that date is from a previous rate sheet and should be re-checked against the city's current page.
What is the late charge on a St. Anthony utility bill?
$9.21 per month, as published on the city's utilities page.
Do I have to pay hookup fees before getting a building permit in St. Anthony?
Inside the city, yes - the city expects its water and sewer hookup fees paid before it approves the building permit. That makes the System Development Charges part of the permit-week budget, not a later bill.