What does the City of St. Anthony charge a new house, from permit application to move-in?
From application to move-in, the city's own documents print four fixed city charges: a $150 application deposit, $4,493 for a water connection, $1,700 for sewer, and a $160 account deposit — retrieved August–October 2026. The building permit fee itself is priced on square footage and construction type; frontage concrete moves the total most.
The city charges, in the order a new house meets them
| Charge | Amount | Basis | Source and date |
|---|---|---|---|
| Application deposit | $150 | Required for the building permit application to be accepted, once zoning permit approval is in hand | City of St. Anthony, Residential Building Permit Application, Rev. 11.2023 — retrieved 14 August 2026 |
| Building permit fee | Not printed | Calculated on square footage and the type of construction | Same application — retrieved 14 August 2026 |
| Water connection | $4,493 | $1,870 plus materials; the city names the 1-inch meter at $2,623 as the cost driver | City of St. Anthony, Utilities page — retrieved 17 October 2026 |
| Sewer connection | $1,700 | $1,600 plus materials — currently $100 | City of St. Anthony, Utilities page — retrieved 17 October 2026 |
| Utility account deposit | $160 | Flat where the property has no usage history; otherwise set by the previous year's usage | City of St. Anthony, Utilities page — retrieved 17 October 2026 |
| Frontage concrete | Not priced | Sidewalk, street, and concrete curb and gutter along the street frontage, required before certificate of occupancy; priced by the linear foot | SAMC 17.09.010(5), cited in the permit application — retrieved 14 August 2026 |
Every figure above is printed exactly as its source prints it. The one-time hookup figures are priced in full, line by line, on what a city hookup costs in St. Anthony; this page lines the whole application-to-move-in sequence up in order.
When each charge is paid
The application cannot be accepted until two things are true: "All Building Permit Applications need Zoning Permit approval PRIOR to permit issuance", and "A $150 deposit is required for application to be accepted" (Residential Building Permit Application, Rev. 11.2023, retrieved 14 August 2026). The zoning step comes first — see zoning permit comes first.
Hookups land earlier than most buyers expect: "If you are hooking into city water and/or sewer, the application for services and the hookup fees have to be paid before the building permit is approved. Then, when the permit is ready, payment for the building permit and the hookup fees is required at the time you pick it up." The city also lists "System Development Charges, which the city lists separately, for new hookups only" — their own line, outside the figures above.
What moves the total
- Frontage concrete. "Concrete flatwork is priced by the linear foot of frontage and varies with access, subgrade and how much of the street section is already in place" — so a wide corner lot carries more of it than a narrow interior one. No document we banked prints a price. The requirement is explicit in the application you sign: sidewalk, street, and concrete curb and gutter "shall be required in and along the street frontage of all properties before certificate of occupancy issued" (SAMC 17.09.010(5), retrieved 14 August 2026). More on sidewalk, curb and gutter before occupancy.
- The permit fee's two inputs. "Building permit fees themselves are calculated on square footage and the type of construction, and are payable when you pick the permit up, along with any water and sewer hookup fees."
- Meter size on the water side. "The water charge is $1,870 plus materials, and the city names the meter as the cost driver at $2,623; together that is the $4,493 figure."
- Design work. Inside the city limits the comparison table prints "Submittal by a registered design professional" — that professional's fee is market-set and not banked here.
If you are outside the city limits
The county path prices differently. The Fremont County Pre-Construction Check List (rev. 17 April 2026, retrieved 14 August 2026) prints: "Site Plan Review: An accurate, detailed site plan is required for all building permits. A $50.00 fee will be charged for the site plan review." That is the county-side figure — whether the city charges an equivalent review is not stated in any document we banked. The county packet and its clocks are laid out on city limits or county and two clocks on your permit.
How to get a real number
Ask the city office for the permit fee against your square footage: City of St. Anthony, 420 N Bridge Street Suite A, St. Anthony, ID 83445 — (208) 624-3494; inspections (208) 709-3030, 24 hours' notice (as printed on our cost page). For weighing city water and sewer against a well and septic system, see city water and sewer, or well and septic — or call our research line at (208) 656-1745.
What we could not price
Named gaps in the banked documents — named, not filled:
- The building permit fee amount — ask the city office for your square footage; we will not estimate it.
- The sidewalk, curb and gutter price — scales with frontage; no banked figure.
- Whether the $150 application deposit is credited against the permit fee or returned — not stated.
- The registered design professional's fee — not banked.
- Any charge for the zoning permit itself, separate from the building permit — not stated.
Frequently asked questions
How much is the St. Anthony building permit fee?
Not printed in any document we banked. The city calculates it on square footage and the type of construction, payable when you pick the permit up. Call the city office at (208) 624-3494 with your square footage for the actual figure.
Is the $150 application deposit refunded?
The application does not say whether the deposit is credited against the permit fee or returned — a named gap. Ask at the counter when you file.
When do I pay the water and sewer hookup fees?
Before the building permit is approved, if you are hooking into city water and/or sewer; the balance is due when you pick the permit up (Residential Building Permit Application, Rev. 11.2023, retrieved 14 August 2026).
What are System Development Charges?
Charges the city lists separately, for new hookups only — printed as their own line rather than inside the hookup figures (Utilities page, retrieved 17 October 2026).
How much is the utility account deposit for a brand-new house?
$160.00 where the property has no usage history; where history exists the deposit is set by the previous year's usage (City of St. Anthony, Utilities page, retrieved 17 October 2026).
Can the city issue my certificate of occupancy before the sidewalk and curb are in?
No. The application you sign certifies that sidewalk, street, and concrete curb and gutter construction is required along the street frontage before the certificate of occupancy is issued (SAMC 17.09.010(5), retrieved 14 August 2026).
Does the $50 site plan review fee apply inside the city?
That figure is printed by the Fremont County Pre-Construction Check List (rev. 17 April 2026, retrieved 14 August 2026) — the county path. Whether the city charges an equivalent review is not stated in the documents we banked.
Who do I call about my address's specific charges?
The city office, (208) 624-3494, for the fee and the inspection schedule — inspections (208) 709-3030 with 24 hours' notice. For research and builder-selection questions, our line is (208) 656-1745.